What is typically the first step in the building demolition process?

Prepare for the Virginia Contractors License Test with targeted questions and detailed explanations. Use flashcards and a comprehensive quiz format to boost your confidence and ace your exam!

The first step in the building demolition process typically involves notifying the utility company. This is crucial because it ensures that all utility services, such as water, electricity, gas, and telecommunications, are safely disconnected before demolition begins. Failing to do so can pose serious safety risks, including potential hazards like gas leaks or electrocution, which could endanger the workers involved and the surrounding community.

By notifying the utility company, the contractors can schedule disconnection in an orderly manner, ensuring that no active lines remain during demolition. This step is foundational and must be completed before engaging in other activities such as hiring a demolition contractor, removing interior fixtures, or securing the site. Each of these subsequent steps follows as a direct consequence of ensuring that utilities are properly managed first.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy